The energy regulator Ofgem has approved a key rule change that will speed up connections for community energy schemes and other local clean energy projects. Under the new rules, projects under 5 megawatts (MW) will no longer be required to undergo a full “Transmission Impact Assessment”. Previously, any project over 1MW had to go through the time-consuming and costly process – regardless of its impact on the electricity network. Most community energy and small-scale schemes fall between 1MW and 5MW, meaning the rule change removes a significant barrier for dozens of local clean power initiatives.